Murray Goulburn Co-Operative
One of two plants constructed to service Murray Goulburn’s white milk contract with Coles, this is a Greenfield Project of $30M construction value. To meet locked-in supplier contracts the project was conceived, designed and constructed within 18 months. We used our experience in the sector to fast track initial concept designs and prepare an early works tender package to commence work on site ahead of finalizing all the process equipment selections.